Causes and Solutions for Cable Overheating: A Guide for Inverter Users

Root Causes of Cable Overheating

Cable overheating accelerates system aging and may cause fires. Based on field data, we identify five primary causes:

  1. Substandard Conductors
    Impure copper (e.g., recycled copper) increases resistance. According to Joule’s law (Q = I²RT), resistance increase causes exponential heat generation.

  2. Overloading
    Continuous current exceeding cable capacity is the leading cause. Example:

    2.5mm² cable (rated 26A) powering a 3HP AC (14A) + water heater (10A) = 24A is near its limit.

  3. Poor Heat Dissipation

    • Densely packed cables in conduits (fill rate >40%)

    • Ambient temperatures >40°C (e.g., rooftop conduits)

    • Proximity to heat sources (<0.5m)

  4. Faulty Connections
    Loose terminals, oxidation, or corrosion at inverter/connector junctions increase contact resistance. These points can reach 100°C+ while normal operation is ≤70°C.

  5. Insulation Degradation
    Aging cables (>10 years) develop cracks allowing moisture ingress, causing leakage currents and abnormal heating.

 

Self-Inspection Guide

Monthly 10-minute checks prevent 80% of failures:

  • Visual Inspection
    Check for:
    ✓ Discoloration (yellowing/browning) at terminals
    ✓ Deformed insulation or burnt odor
    ✓ Corrosion on lugs

  • Current Measurement
    Use clamp meter to verify load current:

    Example: 4mm² cable max = 32A; if reading >38A → Overload

  • Thermal Scanning
    IR thermometer readings:
    ⚠️ >60°C (PVC) or >90°C (XLPE) indicates danger

  • Insulation Test
    Megger values:

    • DC strings: Positive-Negative >1MΩ

    • AC output: Phase-Ground >0.5MΩ

 

Proven Solutions

1. Correct Sizing

Formula: Min. CSA (mm²) = Max Current (A) / Derating Factor
*Factors: Copper=6-8, Aluminum=3-5*

2. Load Management

  • Stagger startup of high-power devices

  • Balance phases within 10% in three-phase systems

3. Connection Integrity

  • Apply torque specified for terminals (e.g., 2.5Nm for MC4)

  • Use antioxidant gel for aluminum conductors

  • Seal with dual-wall heat shrinks

4. Thermal Optimization

  • Maintain cable spacing ≥1× diameter

  • Derate 10% for ambient >40°C

5. Quality Cables

  • Oxygen-free copper (resistivity ≤0.0172Ω·mm²/m)

  • XLPE insulation for DC strings (90°C rating)

  • Compliance with IEC 60228 or GB/T 5023

 

Current Carrying Capacity Table (Copper PVC Cable, 30°C Ambient)

CSA (mm²) Current (A) Power (kW) Application Examples
1.5 14A 3.0kW Lighting circuits
2.5 26A 5.7kW ≤5kW inverter AC output
4 32A 7.0kW 5-7kW inverter main lines
6 47A 10.3kW 8-10kW inverter I/O lines
10 65A 14.3kW Three-phase inverters
16 92A 20.2kW Commercial systems

💡 *Power basis: 220V×Current (1-phase), 380V×Current×1.732 (3-phase)*

Inverter Sizing Guide (Copper Cables)

Inverter Power DC Input (PV) AC Output Critical Requirements
≤3kW 4mm² 2.5mm² UV-resistant insulation
3-5kW 6mm² 4mm² Double-insulated
5-10kW 10mm² 6mm² Flame rating B1
≥10kW 16mm²+ 10mm²+ Steel-armored construction

Example: 7kW 3-phase inverter AC current = 7,000W/(380V×1.732×0.8)≈32A → Select 6mm² (47A)

 

Cables are the lifelines of PV systems. Investing in proper sizing + premium cables + scheduled maintenance boosts efficiency by 15%. When selecting inverters, request our free cable sizing tool and thermal inspection protocol to build a future-proof energy solution.

 

Latest posts

Featured product